Jim and
David,
Dennis has brought up
this subject a number of times over the past months during my discussions with
him. The City and K/J have also discussed this topic collectively during
our design review meetings. Based on our earlier analyses, the decision
was made not to include thickening. However, Dennis is being very
persistent on this topic and throwing you some new or different information, so
lets take a step back and review this decision again. K/J has no specific
preference for or against thickening. Our only goal is to put forth the
best solution for your project. Thickening was originally included as part
of the project in the Engineering Report and taken out during preliminary design
after examining the economics of solids handling with and without
thickening. We offer the following analysis as a means of re-evaluating
and confirming the earlier decision to exclude thickening, so that we can all
confidently move ahead with the design. As the design has progressed
significantly since the last time this issue was evaluated, we were able to
examine it in more detail. For the bottom line, please refer to the
financial evaluation and conclusion at the end of this
e-mail.
Benefits of
Thickening:
The following is a list
of benefits related to sludge thickening, which are consistent with the benefits
Dennis references, and most of which have cost impacts:
1) Thicker sludge can
improve sludge dewatering, which would yield more concentrated cake and reduce
hauling.
2) Thicker sludge often
results in less polymer usage.
3) Thicker sludge reduces
the digestion volume required or increases the SRT (in comparison to the same
volume for non-thickened sludge).
4) Thicker sludge reduces
the hydraulic loading rate on dewatering equipment, which can reduce the
size/number of equipment needed.
Disadvantages of
Thickening:
The following is a list
of disadvantages related to thickening, specifically membrane thickening that is
being suggested by Dennis, and are primarily cost related:
1) Higher operating costs
related to labor, blower energy use, and pumping energy
use.
2) Higher maintenance cost
related to membrane replacement and maintaining additional
equipment.
3) Higher capital cost
related to the purchase of thickening equipment, electrical wiring,
instrumentation, space for housing the equipment, installation of equipment,
additional piping, and additional programming.
Assumptions for
Analysis:
Since all of the
disadvantages are cost related and essentially all of the benefits have cost
impacts, the decision really boils down to one of economics. To perform a
fair economic analysis, we will make the following
assumptions:
- Process modeling predicts that
un-thickened sludge will be around 1.0 to 1.2% solids. Assume 1.1%
solids.
- Based on operation of the
full-scale pilot, thickened sludge averaged about 2.2% solids. Although
brief testing suggested the thickener could operate at higher levels,
limitations unrelated to the full-scale pilot prevented confirmation that
elevated solids concentrations could be maintained long-term. Therefore,
this analysis will be based on thickened sludge at 2.2% solids.
- Even at 2.2% solids, there will
still be less than 40 days SRT, whether with current larger digesters planned
or smaller versions, so lime use will still be employed.
- When the full-scale Fournier press
was piloted at the WWTP, it achieved 12 to 13% cake solids with feed solids at
about 1.9%. When the full-scale Prime Solution press was piloted, it
achieved around 14% solids (as measured primarily by the vendor) with about 2%
feed solids on the first day of piloting and around 13% solids with about 1%
feed solids on the second day of piloting. This data suggests that there
is likely a small increase in cake solids that could be expected with
thickened sludge, which is consistent with reports from City staff that there
was some increase in performance of the belt filter press after startup of the
membrane thickener. Given that the sludge quality will change
significantly with the new WWTP, this data does not translate directly.
However, we will assume that without thickening cake solids will be 15% and
with thickening would be 17%.
- In the economic analysis performed
by the City for land application, the average haul cost was assumed to be
$80/wet ton. That same cost will be assumed for this analysis.
Currently, the plant produces around 3,000 lbs/day of sludge. At the
Phase 1, about 5,400 lbs/day will be produced. The average during that
period is assumed to be 4,200 lbs/day. At 15% solids this will yield
about 14 wet tons per day, for a total haul cost of about $280,000 per year at
$80/wet ton, assuming 31 wet tons per week are composted. At 17% solids
this will yield about 12.4 wet tons per day, for a total haul cost of $230,000
per year at $80/wet ton, assuming 31 wet tons per week are
composted.
- During pilot testing of the Prime
Solution pilot unit, polymer dose ranged from 0.2 to 0.3 gph. It will be
assumed that the average dose was 0.25 gph. Based on the feed rate of
7.5 gpm, this translates to polymer doses of 12 lbs/dry ton for 1.1% feed
solids and 6 lbs/dry ton for 2.2% feed solids. Based on Phase 1 loading
of 5,400 lbs/day from the digesters, the polymer cost would be about $20,000
per year for 1.1% feed solids and $10,000 per year for 2.2% feed solids, based
on the City reported polymer cost of $1.65 per lb.
- Although thicker sludge reduces
the volume required for digestion, there is little savings to be realized
here. Currently, one of the existing SBR tanks is to be divided into two
digester tanks. Although one digester tank should be sufficient in size
with the thicker sludge, there would be no space for sludge storage should the
one digester tank be taken out of service for maintenance. Therefore, it
is recommended that two digester tanks be constructed as proposed.
However, the digester tanks could be constructed to utilize a smaller portion
of the existing SBR tank. This would reduce the size of the blowers, the
number of the diffusers, and the size of the covers. Estimated cost
reduction for smaller blowers is about $50k. The estimated cost
reduction for fewer diffusers is about $55k. Estimated cost reduction
for covers is about $190k. Total cost reduction for smaller digester is
$295k. However, there would be about $205k in additional concrete work
to subdivide a smaller portion of the existing SBR tank into two
digesters.
- Based on the assumed feed solids
rate, the thicker sludge would reduce the hydraulic loading rate on the rotary
fan presses by about half. Therefore, rather than two units, only one
unit would be needed. Currently, the price of two units from Prime
Solution unit is about $288k and the price of two similar capacity units from
Fournier unit is about $545k. The cost savings will be based on the less
expensive of these two manufacturers, which is estimated to be about $155k
with installation. Adding 15% for electrical/instrumentation, the cost
is estimated to be $180k for one fan press (without markups). Also,
running one versus two dewatering units would save about $2,000 per year in
power costs. It is assumed that there would be no significant difference
in operations labor.
- Based on the original proposal
from Enviroquip, the membrane thickener has a stated capacity of 80,000 gpd at
0.5% solids, or a loading rate of about 3,300 lbs/day. For Phase 1, the
anticipated solids loading is expected to reach about 6,600 lbs/day, which is
about twice the rated capacity. The proposal states that the tankage and
blowers of the existing full-scale pilot are sized for 50% more capacity, but
this is still not sufficient for Phase 1. However, with the exception of
the membranes, the City has indicated that there is little of the equipment
included as part of the existing pilot plant that they would want to keep long
term. This would mean the purchase and installation of new piping,
blowers, instruments, pumps, etc.
- The full-scale pilot has a running
horsepower of 63 HP and runs 24/7. Based on current energy cost of about
$0.07/kWh, the annual energy cost is estimated to be $28,800. Based on
the information from the staff about labor time spent with the process and
assuming an average labor rate of $40/hr, the annual labor cost is estimated
to be $29,100. There are not associated chemical cost. The total
operating cost is estimated to be $57,900.
- Based on information provided by
Enviroquip, the annual membrane replacement cost is estimated to be $1,600 and
the annual equipment maintenance cost is estimated to be $4,300, for a total
maintenance cost of $5,900.
- The total O&M cost for the
current full-scale pilot unit is estimated to be $63,800. Since the
blowers are already sized for 50% more capacity and make up 60% of the power
requirements, the energy use is estimated to increase about 60% over current
levels to an estimated annual cost of about $46,000. Operations labor
would likely not increase significantly, but maintenance would go up
proportionally to $11,800. Estimated annual O&M cost for the larger
process is about $87,000.
- Permanent installation of the
membrane thickener would represent a significant cost. The pilot study
report estimated a cost of $688k (before markups). This was based on the
purchase price of the membrane thickener, new sludge pumps, installation,
building expansion, piping modifications, and
electrical/instrumentation. The City has already paid for the cost of
the membrane thickener through lease payments, but as mentioned earlier, the
City would replace all equipment but the membranes. The membranes could
be installed directly into the digester tanks to avoid purchase of new
tanks. Therefore, the main equipment purchase would be two feed pumps,
two permeate pumps, two recycle pumps, and two blowers. A cost of $100k
will be assumed for the price of this equipment with installation. The
existing sludge pumps are to be reused, so this cost is no longer
included. The building expansion was estimated at $65k. Piping
modifications was estimated at $60k. The subtotal is $225k.
Electrical/instrumentation will be assumed at 15% of the subtotal for a total
of about $260k (without markups).
Financial
Evaluation:
Added Capital Cost w/
Thickening: $260,000 Membrane Thickener
Installation
$205,000 Additional concrete work for smaller
digesters
Deducted Capital Cost
w/ Thickening: ($180,000) One less dewatering
fan press unit
($295,000) Smaller digesters
Capital Cost
Differential w/ Thickening:
($10,000)
Added Annual O&M
Cost w/ Thickening: $87,000
Power, labor, maintenance
Deduct Annual O&M
Cost w/ Thickening: ($10,000)
Reduced polymer consumption
($50,000) Reduced haul cost
($2,000) Reduced dewatering equipment power and maintenance
cost
Annual O&M Cost
Diff. w/ Thickening:
$25,000
10-year life cycle cost
differential:
$215,000 assuming 2% effective interest rate (interest minus
inflation)
Conclusion:
There are certainly
benefits that can be realized with the inclusion of thickening. However,
based on our evaluation, thickening is not a cost-effective process for this
application. There is minimal capital cost savings and the higher O&M
costs associated with thickening make the 10-year life cycle cost $215k more
than without thickening. For these reasons, K/J continues to recommend
that thickening not be included as part of Phase 1. The City may wish to
revisit this decision prior to implementation of Phase 2.
Tom Giese