From: James Kelly
Sent: Thursday, May 29, 2008 4:22 PM
To: 'Chris Kelsey'; 'Tom Giese'
Cc: David Randolph; Menglou Wang
Subject: RFI #4, RFI #5, DOE Meeting Notes
Attachments: RFI 04 Response #1 (05-28-08).pdf; RFI 05 Response #1
(05-29-08).pdf; DOE Notes (05-27-08); T3A3-B Spec.pdf; T3A3-B O&M.pdf
Chris
& Tom:
Attached
is the City’s response to RFI #4 and #5, and a copy of my notes from the
meeting with Mike Dawda. Follow-up items David and I owe you:
RFI
#4
1.
City
will do additional investigation of the 15-inch SD entering the site on Haller.
2.
The
City needs to coordinate with the Fire Department on Preliminary Code Review
memorandum items 3.10, 3.11, 3.12, 3.13 and 3.14
3.
The
City will follow-up with Cascade Energy on gas service.
4.
The
City will follow-up with locating an appropriate staging area for the contractor;
KJ to provide estimate SF.
RFI
#5
1.
Are
there any additional structural drawings for the headworks?
DOE
Meeting
1.
Submit
final Sewer Comp Plan ASAP.
2.
Follow
up with Marysville on Raney well water source and reliability requirement for
WWTP.
3.
Send
email to Mike on how we want the plant permitted – Class 1 reliability or Class
2.
Thant is all for now.
Jim