From: Chris Kelsey
[ChrisKelsey@KennedyJenks.com]
Sent: Tuesday, January 29, 2008 11:40
AM
To: James Kelly
Subject: RE: Invoice & Schedule
#4
Attachments: Arlington Schedule Update #4.pdf
Thanks Jim. Attached is the schedule.
We have started weekly internal design meetings with our
discipline leads for this project, including conference calling in our
structural/architectural folks. Some issues discussed that I wish to
bring to your attention:
-
Dewatering - in order to optimize design/space for the solids
handling building expansion, there is enough difference in the footprints for
the different technologies (screw press, fan press) where it would help if the
City could indicate a preferred technology and/or
manufacturer.
-
Equipment and lab/office buildings. Information from the City's
analysis for required rooms/space needed for these facilities. Some associated
issues that we discussed that you should consider in furnishing this info
to us:
-
The lab component will be the most expensive $/sq
ft, so recognition that a big lab will impact $.
-
Current proximity of the lab/office to the MBR support
building. If the MBR support building gets classified as "H-4" building
occcupancy type, which it likely could if all chemicals were stored inside,
then we would be looking at 2-hour fire walls or a 20 to 30 foot
required setback to the lab/office or other structure. That might make the
space available to the property line on the east side (unacquired Future
Admin area) too small to fit the building while maintaining the
setback. Storage of the hypochlorite outside should probably be considered
if it avoids that occupancy class. Again, the lab/office was
shown as a separate bldg so that employees could have separation
from noise, mostly from the blowers. From the noise standpoint, we could
look at switching the lab/office to the south and equipment building to the
north, but again probably not enough room for the 4 bays that are desired
with the equipment bldg.
-
Direction on backup power/emergency generation. City discussion with
the PUD to determine if the City is going to buy and operate the unit, or
if a shared purchase/ownership with the PUD will be sought. Also,
our rough electrical load calcs at the moment show the potential
need for a 1.5 megawatt unit. Would the City consider utilizing the
plants existing 250 kW generator to help meet this load and/or would
the City consider staggering the backup power supply, such that a 1
megawatt unit is furnished initially, and a 500 kW is added at a later date.
The disadvantage to installing a full 1.5 megawatt generator is
the large fuel tanks that would be required with it and the need to
exercise the unit/turn over the fuel.
-
Gas service. We don't believe any of the current plant receives gas
supply from the local provider. Would there be a desire to run a gas supply to
new facility for building heating purposes?
I'm now finalizing things from the 25% design review.
Let me know if you'd like me to formalize items above into an RFI memo to you
that is included with the 25% design review final checklist and meeting
minutes (already sent to you in draft form).
We have our team kickoff meeting with Enviroquip next Tues
Feb 5th, so that we can align CAD folks from both sides, process folks from
both sides, etc. and plot out the plan review
period.
Thanks
-
Chris
(
253-874-0555 | Direct: 253-942-3467
Cell: 253-670-5402 | Fax:
253-952-3435
Chris –
I received the invoice with the
revised schedule (schedule
#4). Can you email me a copy of Schedule
#4.
Thank you
–
James X. Kelly,
PE | Utilities
Manager
City of Arlington |
Utilities
Division
154 West Cox
Ave.
Arlington, WA 98223
Phn: 360-403-3505
Fax:
360-435-7944
JKelly@ci.arlington.wa.us