From: James Kelly
Sent: Friday, May 18, 2007 12:41 PM
To: Chris Kelsey; 'Vanetta R Warren'
Cc: Len Olive; Kristin Wallace; 'kisaksenas@aol.com'
Subject: WWTP, Phase 4-B Ammendment

Chris & Dick –

 

Two items:

 

  1. I presented our proposed contract amendment authorization schedule to Len and the City Administrator (Allen), Allen’s schedule is very tight and would like to follow the revised schedule (pushed back two weeks):

June 11th - Present to Council Workshop (Dick – are you available for this Workshop)

June 18th - Council Approval and Authorization

June 20th – Design Phase Kick-off Meeting (please check your calendars and email back with confirmation)

  1. In an email, Chris presented the option of possibly increasing the City Management Contingency from 5% to 10% – this is a typical amount.  I am inclined to increase the City Management Contingency, but at a bit more modest 7%, please see below:

 

5%

7%

10%

KJ Design

 $ 1,721,397

 $1,721,397

 $1,721,397

City Mgmt Contingency

 $     86,070

 $   120,498

 $   172,140

Total

 $ 1,807,467

 $1,841,895

 $1,893,537

 

  1. The Task Order authorizing Katy Isaksen to start working on the WWTP Funding Program has been sighed by Len and she will be at the June 20th Kick-off meeting.

 

Please email back with your comments.  Thank you.

 

 

James X. Kelly, PE | Utilities Manager

City of Arlington | Utilities Division

154 West Cox Ave.

Arlington, WA 98223

Phn:  360-403-3505

Fax:  360-435-7944

JKelly@ci.arlington.wa.us