Use 7
Thank you
–
Jim
From: Chris
Kelsey [mailto:ChrisKelsey@KennedyJenks.com]
Sent: Friday, May 18, 2007 2:16
PM
To:
Cc:
Subject: RE: WWTP, Phase 4-B
Ammendment
These revised dates
sound fine Jim, I have already alerted the geotech and surveyors to a latter
June/July schedule for their site explorations. We should also be thinking about
July dates to have Val Frankel up for the membrane technology workshop, as I
know we get into vacation season.
I'll spread the work on
June 20th. Will be nice to see Katy there. Please let me know on the
contingency, we will incorporate in with the other changes that I itemize
in an email on Monday that includes the updated contract
exhibits.
Chris
___________________________
Kennedy/Jenks
Consultants
www.kennedyjenks.com
32001
32nd Ave. South,
Federal Way
ChrisKelsey@KennedyJenks.com
(
253-874-0555 | Direct:
253-942-3467
Cell: 253-670-5402 | Fax: 253-952-3435
From:
Sent: Friday, May 18, 2007 12:41
PM
To: Chris Kelsey; Vanetta R
Warren
Cc:
Subject:
WWTP, Phase 4-B Ammendment
Chris & Dick
–
Two
items:
June
11th - Present to Council Workshop (Dick – are you available for this
Workshop)
June
18th - Council Approval and
Authorization
June
20th – Design Phase Kick-off Meeting (please check your calendars and
email back with confirmation)
|
5% |
7% |
10% |
KJ
Design |
$ 1,721,397
|
$1,721,397
|
$1,721,397
|
City Mgmt
Contingency |
$
86,070 |
$ 120,498
|
$ 172,140
|
Total
|
$ 1,807,467
|
$1,841,895
|
$1,893,537
|
Please email back with your
comments. Thank you.
James X. Kelly,
PE |
Phn:
Fax:
360-435-7944
JKelly@ci.arlington.wa.us