From: Chris Kelsey [ChrisKelsey@KennedyJenks.com]
Sent:
Tuesday, May 22, 2007 2:12 PM
To: James Kelly; Vanetta R
Warren
Subject: Final Design Documents
Attachments:
Letter Scope Amend 4.pdf
Jim/Dick:
Please find attached, in this and 3 ensuing emails,
our proposed Amendment No. 4 Scope/Schedule and Budget exhibits for Final Design
of the WWTP and BCF facility expansions. I have also attached placeholders for
exhibits to be added under Phase 4C - Construction Services, per your request.
Also, previous amendment authorization letters have been addressed to Len, which
we have temporarily done again here, but please let me know if we should change
this letter and address to you Jim.
As I am very conscious about budgets, especially
after you have reviewed a budget number under a previous draft of our proposal,
I want to make sure to identify the items that have caused change in this final
proposal. The scope and budget for the last proposal that you reviewed, which
was the basis of our conversations during our May 11 meeting at our offices, had
a bottom line fee estimate of $1,721,397 before the City Management Reserve. The
attached proposal has a fee estimate total of $1,779,047. An identification of
the items that resulted in the overall increase is as follows:
- Task 4.14, PM and QA/QC - We have added additional
senior hours of QA/QC to cover 2 issues we discussed in our May 11 meeting, 1)
an additional review period has been created from the decision to fast track
the compost facility design and bid as a separate package in advance of the
WWTP (the 100% submissions will now be separate, while the BCF design will
reach 60% at 30% WWTP and 90% at the 60% WWTP), and 2) additional hours to
specifically identify the QA/QC program that was performed internally before
release to the City, and will include such information as what senior
engineers reviewed what documents, and the word processing protocol in
producing the deliverable. An increase of approximately $12,000.
- Task 4.14, Membrane Equip Selection - We have
added an additional item "I" which separately identifies our assistance to the
City in developing equipment criteria and warranty information to be utilized
in selecting and pre-purchasing the new BCF mixer, which will be a slightly
different procurement technique than that utilized for the membrane equipment.
An increase of approximately $6,000.
- Task 4.18 Site Investigations - The previous
budget had a placeholder amount of $20,000. We have since received an official
proposal from GeoEngineers in Everett, which came in at $25,000, and included
provisions for 4 borings at the WWTP in the locations of new buildings, as
well as one boring at the BCF. We think this is appropriate. Additionally, a
follow-up conversation with Cascade Surveying of Arlington on their initial
proposal resulted in a $1,200 increase to account for field time and data
download for performing spot elevations of existing facilities and dipping of
manholes/sumps to be added to their topographical and utility survey.
- Task 4.19 Permitting Assistance - After
conversations with our subconsultant, ESA/Adolfson, on their initial proposal,
$3,000 was added for permitting assistance associated with getting a Shoreline
permit and the possibility of needing an HPA permit through Fish and
Wildlife.
- Task 4.22, Final Design Documents - Our previous
proposal had a placeholder of $12,000 for landscape architecture. We performed
lots of research to identify a local firm, including asking the advice of
Perteet, who we know the City utilizes on road projects, and came to the
conclusion that a viable consultant could not be found locally. We received an
estimate from Osborn Pacific of Seattle, which came in much higher, but had
them cut down the number of design submittals, eliminate design of an
irrigation system, and eliminate their estimated time associated with City
permitting, and have received an updated proposal of $31,200. This includes
submission of 10% conceptual sketches, followed by 90% and 100% submittals
that include landscape plans and details for perimeter plantings/screening at
the WWTP, as well as additional plantings on the west entrance side of the
BCF, on both sides of the entrance driveway.
- Task 4.24, Bidding Services - We have increased
our hours to reflect two different bidding periods for the BCF and WWTP, which
will require more time addressing contractor inquiries, and require an
additional pre-bid meeting/walk through and bid tabulation. An increase of
approximately $8,000.
The schedule has shifted such that completion is now
about 2 months later for two reasons: 1) the 60% submittal was shifted back
about 3 weeks so that there was time to incorporate information from the
membrane shop drawings into the 60% submittal following our review of the shop
drawings, and 2) the original schedule showed completion of the final bid
documents before getting comments back from Ecology. We reduced the Ecology
review period to about 65 days (45 working days) and showed completion of the
final bid documents for the WWTP about 3 weeks later. This puts completion at
the beginning of September, versus first part of July in the previous version of
the schedule. Approved City permit review is based on the 90% WWTP submittal and
it is assumed that L&I and City building, planning, and fire dept. review
periods will be no longer than the Ecology review periods. The same assumptions
were made regarding reviews for the BCF.
I have 2 original copies that I will hold on
overnight mailing to you until Thursday PM, to allow you to provide final
feedback and review comments for incorporation. And in regards to your request
for an electronic version of the schedule Jim, let me know if you need more than
what is included in this PDF package - I'm sure I could get it sent along in
Microsoft Project as well. Thanks again for your support, and we are very
excited to get rolling on this important showcase project!
Chris
<<Letter Scope Amend
4.pdf>>
___________________________
Kennedy/Jenks Consultants
www.kennedyjenks.com
Christopher W. Kelsey,
P.E.
32001 32nd Ave.
South, Suite 100
Federal Way, WA 98001
ChrisKelsey@KennedyJenks.com
( 253-874-0555 | Direct: 253-942-3467
Cell: 253-670-5402 | Fax:
253-952-3435