From: Tom Giese [TomGiese@KennedyJenks.com]
Sent: Tuesday, September 09, 2008 2:18 PM
To: James Kelly
Cc: Chris Kelsey
Subject: RE: Discharge to Wetland
Jim,
My responses:
1) You could design for up to 4.0 MGD, as this
will be the rated maximum Class A reclaimed water production with the addition
of the future 4th UV reactor. With the initially installed 3
reactors, the capacity will be 2.0 MGD of Class A reclaimed water (such that
you would have to discharge to the river when plant flows exceed 2.0 MGD, which
will require some additional control logic, actuated valves, etc.). It’s
possible you could even get by with Class B reclaimed water, in which case the
capacity would be even higher.
2) You could design for lower capacity, though
there won’t be much storage in the WWTP. It would require reprogramming
of the MBR system to allow surging of water level in the tanks and may
adversely impact the process if surging occurs frequently. However, if
the WWTP was producing more than was needed, you could only pump what is
required and let the rest overflow to the headbox and discharge through the
outfall. Again, this will require some additional control logic, actuated
valves, etc.
3) We looked at wetlands discharge for
4) We’ve arranged our design not to exclude
this. The routing of the discharge line will not be simple, due to
crossings of 48”, 36” and 24” pipelines among others, but should be
achievable. It may require the discharge line running above grade along
side the BNR tank.
Tom Giese
From: James Kelly
[mailto:jkelly@ci.arlington.wa.us]
Sent: Tuesday, September 09, 2008 1:39 PM
To: Tom Giese
Cc:
Subject: Discharge to Wetland
Tom –
The wetland delineation, geotech, and survey are complete
for the City’s Stormwater Wetland; We are beginning to work with the Stormwater
Wetland design. As you know, it is our intention to have the effluent
from the Reclaimed Water Facility discharge into the wetland during peak summer
months to mitigate temperature and DO impacts to the
1. In designing the wetland hydraulic capacity, what should we design for – the Daily Max month of 4.0 MGD?
2. Could we design lower hydraulic capacity and have surge storage within the BNR and MBR?
3. How do you think DOE will accept our proposal to discharge Reclaimed Water into a stormwater wetland to mitigate temperature and DO impacts?
4. As we move closer to determining where the discharge point to the wetland will be, we might come back and ask K-J to design the discharge line from the two 15 hp pumps to the WWTP boundary (and controls)……please keep this in mind as you think of an alignment.
Thank you-
James X. Kelly, PE | Utilities Manager
City of
Phn: 360-403-3505
Fax: 360-435-7944